After a three week absence, the builders reappeared at 9.30 this morning. At close of business today, the place looked like this:
So, all day to cover the foundations with a tarpaulin? Not quite! Beneath that green exterior lurks a damp proof membrane, insulation and the electric underfloor heating mats for the bedroom and en-suite. Tomorrow Dizzy is back to cover all of the above in another layer of concrete.
Apparently the frames have been built off site, and they may start putting those up next week. The windows are on order, but won't be here for another six weeks. Nice to see things happening again though.